The company said that the workovers are in progress.

This term applies to surface or down-hole hardware failure being the most obvious reason for a workover.

If the problem is down-hole, all equipment must be pulled from the wellbore.

The company said that in some cases, the purpose of intervention may be to upgrade pumping equipment, reperforate the well, or access a new zone.

Quest Oil director and VP of operations Frank Grabs said that it has scheduled 45 days to complete the ‘Phase One’ plan.

“Having a proactive approach to workover programs will allow our team to notice and address any problems before serious production shut down can occur,” Grabs said.