Under the terms of the contracts, Vestas will be responsible for the delivery, installation and commissioning of the wind power plants as well as provide a 10-year Active Output Management (AOM) 4000 full availability service package for each project.

The four projects include 14MW Skalleberg, which will use eight V100-1.8MW and two V90-2.0MW turbines; 13MW Ramsns will feature seven V100-1.8 MW turbines; 14MW Mungserod will include eight V100-1.8MW turbines; and 13MW Alered will feature four V112-3.3MW turbines.

The Ramsnas, Mungserod, and Alered projects are likely to be developed during the third quarter of 2014, while the Skalleberg project will be built during the fourth quarter of 2014.

Eolus CEO Per Witalisson said the offer made by Vestas has matched the company’s expectations and has looked forward to the same good cooperation as it had in previous business with Vestas.

Vestas Northern Europe president Klaus Mortensen said the latest contracts reaffirm its strong relationship with Eolus.