As per the contract, KBR will engineer, procure, and construct the DSI system at the power station.
Located in Kincaid, the project will include sodium bicarbonate (SBC) rail unloading facilities, SBC truck unloading facilities, Nol-Tec Systems Sorb-N-Ject technology DSI system, and onsite SBC milling and storage.
The project is scheduled for completion in late 2013.
KBR Power & Industrial Group president Jim Stewart said, "KBR is committed to delivering safe and quality projects to our clients and we welcome this opportunity to deliver this important project for Dominion and its Kincaid facility."
KBR is a global engineering, construction and services company supporting the energy, hydrocarbon, government services, minerals, civil infrastructure, power and industrial markets.