In the event the installed PV system consisted of 1884 Benq 327 W solar modules. The array was installed on the roofs of two large service buildings inside the resort complex. To accommodate all the solar panels needed, an additional building with an area of 1600 sq metres had to be built.

Construction of the project began in July 2015, with commissioning of the system towards the end of the year. The fully operating system now generates around 930 MWh of electricity per year, and the hotel is expected to reduce its annual carbon footprint by about 530 tons of carbon dioxide.