The loan represents 80% of the overall investment of nearly €1.2bn for the portfolio which includes Nxuba, Oyster Bay, Garob, Karusa and Soetwater, each with a 140MW of capacity. Enel will contribute €230m in equity for this portfolio.

Enel’s Global Renewable Energies Division Enel Green Power head Antonio Cammisecra said: “We have reached an important milestone in South Africa by achieving financial close on five major wind projects which confirm our continuing commitment to the country’s renewables sector, within a context of sustainable development.

“Enel Green Power will be supporting these processes by generating its emission-free energy in partnership with local shareholders and in cooperation with the local communities, according to our long-term vision of shared value creation.”

These wind farms were all awarded in round 4 of the South African government’s Renewable Energy Independent Power Producer Procurement Programme (REIPPPP). Enel stated that the each of the project will be minority-owned by a local partner.

Following the financial close, Enel expects to begin construction of the first wind farm, Nxuba by the end of this year. The Nxuba and the Oyster Bay wind farms will be built in the Eastern Cape province, while Garob, Karusa and Soetwater projects will be constructed in the Northern Cape province.

After the start of construction on the Nxuba, Oyster Bay and Garob wind farms are expected to begin in the first half of next year. Construction of Soetwater and Karusa wind farms is expected to start in the second half of next year.

Operations at Nxuba could start in the second half of 2020, followed by Oyster Bay in the first half of 2021. This will be followed by Garob, Soetwater and Karusa, whose operations are expected to begin in the second half of 2021.

With all the five wind farms becoming operational in the later part of 2021, Enel’s installed capacity is expected to reach to more than 1.2GW in South Africa.