This phase included electrical, equipment and facility repair and bringing two producing wells back on-line.

According to the company, production has now been increased from 1-3bopd to 6-7bopd.

Baron Energy president and CEO Ronnie Steinocher said a number of additional wells will be involved in Phase-2 production enhancement program and Baron plans to begin Phase-2 later this month.

"Upon completion of Phase-2, a Phase-3 will be implemented bringing a total of 6-7 producers back on-line. This field work should be completed by year-end," Steinocher said.