Under the contract, BWCC has agreed to perform construction, electrical and mechanical work at the facility located near West Olive.

In addition BWCC also will provide flues, insulation and structural steel for the 400MW, coal-fired Campbell unit 2’s particulate emissions-filtering baghouse.

BWCC was previously secured an order to design and supply the plant’s NOX-reducing selective catalytic reduction system (SCR).

The company has started work at the project site and is scheduled to tie in both the SCR and baghouse during a planned outage in March 2013.