The expansion project will construct one set of ‘two on one’ F-grade gas and steam combined-cycle generating unit with a power generation capacity of 923MW, heat supply capacity of 650MW and heat supply area of approximately 13 million sqmt, and high-standard denitrification, noise reduction, water treatment and other environmental protection facilities will be constructed concurrently.

Construction of this project is said to have an active demonstrating effect on the construction of subsequent gas co-generation centers in Beijing and will satisfy the heat demand of Beijing city, enhance energy supply safety and make a significant contribution to the optimization of the energy structure.

The estimated total investment of this project is approximately RMB3.19bn, of which 25% is project capital that will be contributed by Huaneng Power International, Beijing Jingneng International Energy and China Hua Neng Group Hong Kong according to the ratio of 41%, 34% and 25%, respectively. The remaining investment will be funded by bank loans.