The St Isidore project consists of two solar PV installations located 6km apart in the Municipality of the Nation.

The 11.8 MWp installation, St Isidore B, began delivering clean electricity to the Hydro One distribution grid in late December 2011.

The first 11.5 MWp installation, St Isidore A, came online in December 2010.

These two installations combined will deliver nearly 24 MWp under the Government of Ontario’s Renewable Energy Standard Offer Program.

The St Isidore B site consists of 152,000 panels, which will generate solar energy to meet the peak demands of about 3,500 Ontario households.

enXco Service Canada will provide long-term operations and maintenance services.