The company was facing a March 31, 2009, deadline to determine the future of the plant under the terms of a Consent Decree related to the company’s 2005 New Source Review settlement.

This energy crop would act as a carbon sink, removing as much carbon dioxide from the environment when it is growing as it releases when it is burned. In addition, burning principally with biomass at the plant would produce lower emissions overall than if it was retrofitted with a scrubber.

The capital cost for retrofitting the Burger Plant to burn biomass is estimated to be around $200 million. This is enough electricity to power approximately 190,000 homes, making it one of the largest biomass facilities in the UShttp://www.firstenergycorp.com/NewsReleases/2009-04-01%20Burger%20Plant%20Biomass.pdf based on generating capacity. And, biomass plants can operate continuously, providing power whenever it is needed.

With the completion of the project, FirstEnergy’s portfolio of renewable energy could total more than 1,100 MW, including 451 MW of pumped-storage hydro and 376 MW of wind power.

“Retrofitting the Burger Plant for biomass will expand our diverse generation portfolio even further and continue our support of state and federal efforts to increase reliance on renewable energy sources,” said FirstEnergy President and Chief Executive Officer Anthony J. Alexander. “And, the project will provide a new and exciting future for the plant and continued economic support in Belmont County.”

“This project will help jump-start the biomass renewable energy industry here in Ohio and also serve as a model for projects throughout the U.S.,” said Ohio Governor Ted Strickland. “In addition to retaining jobs at the Burger Plant, this project has the potential to create additional jobs and investments, particularly as biomass fuel suppliers work to meet the needs of this operation and as other renewable energy projects are developed in Ohio. The Burger project advances Ohio’s advanced energy portfolio standard, which requires that 25 percent of Ohio’s energy come from advanced and renewable energy sources by 2025.”

“We deeply appreciate the support we received from state and federal officials, union leadership and plant employees, and our friends in Belmont County in our efforts to keep the Burger Plant open,” said Alexander.