Magnox is the operator of nuclear sites that are owned by the Nuclear Decommissioning Authority.

The company has established a framework model including a number of specialist contractors including Doosan Keltbray Consortium, Celadon, Erith, Squibb/LVI Group, Nuvia, EDS/Kitsons

Magnox will commence the work at the sites of the UK’s first generation of nuclear power stations in the coming months.

The work will begin with the de-planting of the boiler houses at Bradwell Site in Essex and the demolition of admin and ancillary buildings at Dungeness A Site in Kent.

Magnox Program director Alan Bladon said the contract enables the company to outperform its decommissioning plans by building long term supply chain relationships, learning from experience.