32 AW 125/3000 turbines are to be installed for the “La Castellana” project, while the “Archiras” project entails 15 turbines of the same type. Construction is to commence in the fourth quarter of 2017 for expected completion in summer 2018.

In both cases, Nordex will be installing the wind farms for its new customer Central Puerto, a utility which is the most important private generation company in Argentine, and has been primarily  operating conventional and hydraulic power stations since its establishment in 1992.

The contracts are the result of the first tender for delivery contracts for “green electricity” in Argentina. In October 2016, the government awarded contracts for a total capacity of more than 1.1GW, most of which were for wind power projects (700MW).

In a second call for tenders in November, contracts for a further 600MW, including 400MW for wind power, were awarded.