The wind power project is fully operational, providing clean energy to BC Hydro under a 25-year electricity purchase agreement.

GE and managing partner Plutonic oversaw erection of 43 wind turbines, construction of an electric substation, installation of seven kilometres of transmission lines.

The project is located 1,100km northeast of Vancouver near Chetwynd in the foothills of the Canadian Rocky Mountains.

The Dokie project has the generating capacity of 320,000-340,000MWh per year, which is enough energy to power about 34,000 homes.

The project was completed within 13 months.