PT Bhumi Jati Power has awarded Pöyry a technical consulting services assignment for Tanjung Jati B Units 5 & 6, a 2×1000 MW coal-fired power plant project in Central Java. PT Bhumi Jati Power is a project company established in Indonesia. Sumitomo Corporation of Japan is the lead developer.
The Tanjung Jati B re-expansion is a BOT (build, operate and transfer) project called Jawa-4 under the Indonesian power development plan. The plant consists of two very large 1000 MW (net) units designed for ultra-supercritical steam conditions. The new units will be built adjacent to the existing Tanjung Jati Units 1 to 4 that have total capacity of 2640 MW and provide about 11% of the total electricity in Java-Bali power grid.
Pöyry's assignment includes assistance in project management, design review, site services, quality assurance and quality control, commissioning services and assistance in environmental monitoring for the project. The overall schedule for the project is about 5 years.
This is a continuation of Pöyry's earlier assignment in the same project. Pöyry has been involved in the project as owner's engineer during the development phase, providing technical advisory services to Sumitomo Corporation.
The value of the order has not yet been disclosed.