The company has conducted the 60 tonne three stage fracture stimulation, which comprised of three 20 tonne stages using specialized completion tools placed throughout the 475m horizontal leg.
The well is currently being flow tested up tubing to recover frac water and nitrogen, and subject to recovery of frac fluids and nitrogen the stage frac tools will be recovered followed by a flow test to determine gas and oil flow rate.
Reef has also completed work on its natural gas processing system at the Grand Bend process facility and installed a variable frequency drive unit to match gas flow rates, compressor loading and cooling, and to match gas process criteria.
Additionally, minor piping changes have been completed along with cleaning of Joules Thompson heat exchanger unit to help optimize the gas liquids recovery system.
This work was performed to increase efficiencies and meet the dry natural gas test specifications of the pipeline utility operator, and a dry gas test will be conducted this week, the company said.