The well is anticipated to take 20-25 days to drill and complete. If successful the well is anticipated to be completed, flow tested and connected to the existing infrastructure. These completion activities are expected to be carried out within 21 days of the drilling rig departing the location. This is the third of a nine well drilling programme on the Company's Sebou, Gharb Centre and Lalla Mimouna permits in Morocco.
 
As per the announcement on 13 November 2017, SDX can confirm that its KSR-15 well is currently being connected to the existing infrastructure and is expected to be placed on test production within the next 10 days.