Alfanar Construction and SSEM will perform the project on turnkey basis for Saudi Electric Company. Delivery of the components is scheduled for 2010 and 2011, with an order volume of approximately EUR100m.

The Hail Extension II gas turbine power plant is located in central Saudi Arabia and is made of two units, with a total power generating capacity of 160MW. The plant is expected to come on line in summer 2011.

The new Al Qurayat Expansion II gas turbine plant is located in the north west of Saudi Arabia. Consisting of two units, the plant will have a total installed capacity of 136MW.

Siemens will supply four SGT6-2000E gas turbines for the two plants, along with four generators and the auxiliary equipment.