The company has also been advised by the operator that drilling at the Cartwright-1H well has reached a measured depth of 13,969ft after the setting and cementing of intermediate 7 5/8″ pipe to 13,953ft.

The company said that while drilling, gas shows have been found and the plan is to complete the pilot section of hole before drilling laterally in the target formation.

Work has also begun on connecting the flow line from the Cartwright-1H well to the sales point.