Under the terms of the contract, Vestas has agreed to supply and commission 33 units of V100-1.8MW turbine for the wind facility located in Huron County.

The contract includes a ten-year service and maintenance agreement and Vestas’ Active Output Management (AOM) 4000 maintenance program.

Delivery is scheduled for mid-2012, and commissioning of the turbines is expected in late 2012.

The Harvest II wind farm will provide enough electricity to power nearly 18,000 Michigan homes.

The Harvest I Wind Project was commissioned in 2008 and includes 32 units of Vestas V82-1.65MW turbine.

The AOM 4000 program guarantees turbine availability and includes all planned and unplanned maintenance services, and it also includes continuous remote monitoring and surveillance of the project via the VestasOnline SCADA system.