The Borssele I and II offshore wind power project produced the first electricity in April 2020. Image courtesy of Ørsted.
The Borssele I and II offshore wind power project comprises of 94 SG 8.0-167 DD wind turbines supplied by Siemens Gamesa. Image courtesy of Ørsted.
Ørsted started the offshore construction works for the project in January 2020. Image courtesy of Ørsted.

Borssele I and II is a 752MW offshore wind power project located in the Dutch North Sea, Zeeland province, Netherland.

Owned and operated by Ørsted (DONG Energy), the project has been fully functional since November 2020.

The Netherlands’ Minister of Economic Affairs awarded a concession for the development of the Borssele I and II wind power project in July 2017. Ørsted won the tender to produce electricity at a price of £65.7 (€72.7) per MWh, excluding the transmission costs.

While the construction works on the wind farm commenced in January 2020, the first power was produced in the month of April 2020.

The Borssele I and II offshore wind farm is expected generate enough green electricity to power approximately one million Dutch households a year.

Location and site details

The Borssele I and II offshore wind power project is located in the Dutch Exclusive Economic Zone in the North Sea, approximately 22km (14miles) off the coast of Westkapelle, Zeeland, Netherland.

The project site occupies approximately 112km2, while the water depth ranges from 14m to 36m.

Borssele I and II offshore wind farm make-up 

The Borssele I and II offshore wind power project comprises 94 SG 8.0-167 DD turbines of 8MW capacity each from Siemens Gamesa.

Each wind turbine has a tip height of 200m and a rotor diameter of 167m. The blade length of the turbine is 81.4m while the  swept area of each turbine is 21,900m2.

The turbines are installed on 76m-high and 8.3m-diameter monopile foundations with each foundation weighing approximately 1,188t.

Power evacuation

The electricity generated by each wind turbine is gathered and transmitted through approximately 190km of 66kV inter-array cables connected to TenneT’s Borssele Alpha offshore substation.

The electricity is stepped up to 220kV at the offshore substation and is transmitted through a 60km-long export cable connecting an onshore substation. The electricity from the onshore substation is further transmitted through two 220kV export cables to the national extra-high-voltage (EHV) grid.

Contractors involved

Siemens Gamesa was contracted for the supply of wind turbines for the Borssele I and II wind power project in July 2017. The contract scope also includes long-term maintenance of the turbines.

EEW SPC and EEW OSB from the EEW Group were contracted for the production and supply of monopiles and transition pieces in December 2018.

Sif Offshore Foundations was also awarded a contract for the production and supply of 47 monopiles in October 2018.

Bladt was ordered by Ørsted in December 2018 for the supply of additional of 24 transitional pieces apart from the previously contracted 35 pieces.

Dillinger was contracted for the supply of heavy plates for monopile foundation used in the transformer station.

Nexans was contracted for the supply of 66kV submarine inter-array copper cables, while Van Oord was contracted for the cable installation works of the Borssele I and II offshore wind power project in October 2018. The scope included the transportation, installation, and burial of the 94 inter array cables with a total length of 167km.

DEME Offshore was engaged for the installation of monopile foundations for the Borssele I and II offshore wind project.

Tags: