The existing Hsinta gas-fired power plant has been operational since 1999. Image courtesy of Taiwan Power Company.
The new Hsinta combined-cycle power plant will use six GE7HA.03 gas turbines. Image courtesy of General Electric.
The Hsinta combined-cycle power plant renewal project will comprise three 1.3GW power blocks. Image courtesy of Matt8830.

The Hsinta power station renewal project involves three new gas-fired combined-cycle units for a total capacity of 3.9GW to replace the old gas-fired and coal-fired units of the Hsinta power plant complex in Kaohsiung, Taiwan.

Owned and operated by state-owned Taiwan Power Company, the Hsinta power station complex houses a 2.1GW coal-fired plant comprising four units commissioned in the 1980s and a 2.4GW natural gas-fired combined-cycle facility equipped with five units that were commissioned between 1998 and 1999.

Taiwan Power Company announced to upgrade and replace the existing gas-fired units for greater operational efficiency and better environmental performance in October 2017.

The Environmental Protection Administration (EPA) of Taiwan passed the initial environment impact assessment (EIA) for the new gas-fired combined-cycle project at the existing power generating site in January 2020.

The key contractors for the Hsinta power plant renewal project were selected in September 2020, while the new gas-fired combined-cycle facility is expected to commence operations in 2024.

The Hsinta power station renewal project is being developed in compliance with Taiwan’s Renewable Energy Development Act (REDA) energy policy that aims at boosting the gas-fired power ratio to 50% by 2025. 

Location and site details 

The 3.9GW new Hsinta combined-cycle power plant will be developed on a 202acre-site adjacent to the existing 2.4GW gas-fired facility in the Yongan district, in Taiwan’s southwestern port city of Kaohsiung.

The new Hsinta combined-cycle power plant make-up 

The new gas-fired facility will comprise three combined-cycle generating units of 1.3GW capacity each.

Each unit will be equipped with two 7HA.03 gas turbines, one steam turbine, and two heat recovery steam generators (HRSG) from GE.

GE’s 7HA.03 gas turbine is a heavy-duty 60Hz gas turbine with a rated simple-cycle output of 430MW. It can deliver a net output of 1,282MW and a net heat rate of 5624kJ/kWh in a 2×1 combined-cycle configuration. It is designed to offer a net efficiency of more than 64% in combined-cycle operation.

The other components of the new facility will include the fuel supply equipment, seawater desalination system, circulating water system, raw water system, switchyards, chimneys, and related auxiliary facilities.

Feed gas supply 

The Hsinta combined-cycle power station will receive gas supply through a 36-inch natural gas pipeline from the Yongan LNG receiving station. The estimated LNG requirement of the Hsinta power plant will be approximately 480 tonnes (t) per hour. 

Contractors involved with the Hsinta power station upgrade 

A consortium of General Electric International and Taiwan-based CTCI Corporation was selected as the main contractor for the engineering, construction, equipment supply, and commissioning of the Hsinta combined-cycle power station in September 2020.

GE will be responsible for the supply of six gas turbines, three steam turbines, six HRSGs, and nine generators for the renewal combined-cycle facility, while the CTCI Corporation’s scope of work includes the engineering and civil construction works, the erection of power generating units along with the balance of plant (BOP) works. 

The existing Hsinta combined-cycle power plant 

The existing Hsinta combined-cycle power plant is equipped with five gas-fired combined-cycle units of 442MW capacity each.

Each unit is equipped with three SGT6-8000H gas turbines with HRSGs and a steam turbine from Siemens.

The existing natural gas-fired units are scheduled for decommissioning during 2026-2027, followed by the decommissioning of the four coal-fired units within the complex during 2023-2026.

Tags: