Hamon was selected for the design and delivery of one of the biggest sea water Flue Gas Desulfurization systems worldwide for two 1.000 MW ultra-supercritical units of the Tanjung Jati B 5&6 power plant. The first unit of the plant has entered commissioning phase.
Wet flue gas flow of the FGD system is 3,300,000 Nm3/h per unit. The unique design of sea water intake basin was confirmed by real model 1:10.
Upon completion, Tanjung Jati B will become one of the biggest thermal power stations in Indonesia with a total installed capacity of 4,640MW.
Tanjung Jati B 5&6 expansion project includes two new high-efficient ultra-supercritical thermal power generator units in the area adjacent to Tanjung Jati B thermal Power Plant (unit 1 to 4) in the Central Java, Indonesia.
Construction on the 2GW re-expansion project started in March 2017.